Topic I-21 — Contract Remedies

Show-Cause Letters

What a show-cause notice is, when it follows a cure notice, when it stands alone, and how to evaluate the contractor's response.

1 What a Show-Cause Notice Is

A show-cause notice is a written notice from the contracting officer telling the contractor that the government is considering terminating the contract for default, and asking the contractor to present any reasons (in writing, within a specified period) why the contract should not be terminated. FAR 49.402-3(f) describes the show-cause notice.

Where a cure notice says "fix this or we may terminate," a show-cause notice says "tell me why I should not terminate you." The burden shifts to the contractor. They need to explain why the government should keep the contract in place despite the identified failure.

The show-cause notice is not a decision to terminate. It is the step immediately before that decision. It gives the contractor one last opportunity to present facts that might change the outcome: excusable delays, government-caused problems, or a credible plan to complete performance. The CO evaluates the response, consults with legal counsel, and then makes the termination decision.


2 When to Issue a Show-Cause Notice

A show-cause notice is appropriate in two situations:

After a cure notice has expired and the contractor failed to cure. You issued a cure notice, gave the contractor a reasonable cure period, and they did not fix the problem. The show-cause notice is the next step in the process. It puts the contractor on final notice and gives them one more opportunity to explain.

When the delivery date has already passed and the contractor has not delivered. In this case, a cure notice is not required because the failure is not "failure to make progress" (which requires a cure notice) but rather a completed failure to deliver on time. You can go directly to show-cause. FAR 49.402-3(f) contemplates this: when the CO is considering termination for default because of the contractor's actual failure to perform or deliver, a show-cause notice should be sent.

SituationShow-Cause Appropriate?
Cure notice expired, contractor did not cureYes. This is the standard sequence: cure notice, then show-cause, then termination decision.
Delivery date passed, contractor did not deliverYes. No prior cure notice required. Show-cause can be the first formal step.
Contractor performance is substandard but delivery date has not passedNo. Issue a cure notice first. Show-cause comes after the cure period expires if the contractor did not cure.
Contractor partially cured but problem persistsJudgment call. If the partial cure is not enough and the deficiency still endangers performance, show-cause is appropriate. Document why the partial cure was insufficient.
Cure notice and show-cause serve different purposes. A cure notice tells the contractor to fix the problem. A show-cause notice tells the contractor to justify why the government should not terminate. Do not combine them into one document. They are separate actions with different legal significance, and collapsing them deprives the contractor of the opportunity to cure before facing the termination question.

3 What Goes in the Show-Cause Notice

A show-cause notice should contain:

  • Identification of the contract: contract number, task order number, contractor name.
  • Statement of the failure: describe the specific default. If a cure notice was previously issued, reference it and state that the contractor failed to cure within the cure period. If the delivery date passed, state the delivery date and the fact that the contractor did not deliver.
  • Statement that termination is being considered: clearly state that the government is considering termination for default under the applicable default clause (FAR 52.249-8 or other).
  • Request for the contractor's response: ask the contractor to show cause, in writing, why the contract should not be terminated for default. Specify a response deadline (typically 10 days, though the FAR does not prescribe a minimum for show-cause responses).
  • Consequences of failure to respond: state that failure to respond, or a response that does not adequately justify continued performance, may result in termination for default.
FAR 49.607(b) — Show-Cause Notice Format

Since you have failed to [insert "perform Contract No. ___ within the time required by its terms," or "cure the conditions endangering performance under Contract No. ___ as described to you in the Government's letter of ___ (date)"], the Government is considering terminating the contract under the provisions for default of this contract. Pending a final decision in this matter, it will be necessary to determine whether your failure to perform arose from causes beyond your control and without fault or negligence on your part. Accordingly, you are given the opportunity to present, in writing, any facts bearing on the question to [insert the name and complete address of the contracting officer], within 10 days after receipt of this notice. Your failure to present any excuses within this time may be considered as an admission that none exist. Your attention is invited to the respective rights of the Contractor and the Government and the liabilities that may be invoked if a decision is made to terminate for default. Any assistance given to you on this contract or any acceptance by the Government of delinquent goods or services will be solely for the purpose of mitigating damages, and it is not the intention of the Government to condone any delinquency or to waive any rights the Government has under the contract.

That is the FAR-prescribed format. Like the cure notice format, it is a single paragraph. In practice, you should supplement this with the specific facts of the situation: the contract number, the delivery date or cure notice date, and a clear description of what the contractor failed to do. The FAR format handles the legal framework; your job is to fill in the brackets with enough specificity that the record stands on its own. Note that the format already covers the two common triggers: failure to perform on time, and failure to cure after a cure notice.


4 Evaluating the Contractor's Response

After receiving the contractor's show-cause response (or after the response deadline passes without a response), the CO evaluates what was submitted and makes a recommendation to legal counsel. Three outcomes are possible:

The contractor presents a valid excusable delay. FAR 52.249-8(c) lists causes that may excuse a contractor's failure to perform: acts of God, acts of the government in its sovereign capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather. If the contractor demonstrates that the failure was caused by one of these and was beyond their control and without their fault or negligence, termination for default is not appropriate. The CO should consider granting a delivery extension or other appropriate relief.

The contractor presents a credible plan to complete performance. The contractor acknowledges the problem but provides a realistic, detailed plan to get back on track. The CO, in consultation with legal counsel, may decide to give the contractor more time rather than terminate. This is a judgment call. If you go this route, document the decision and the basis for it, and set clear milestones so you can assess whether the recovery plan is working.

The contractor's response is inadequate, or no response is received. If the contractor does not respond, or responds with excuses that do not constitute excusable delay and no credible recovery plan, the CO has a basis to proceed with termination for default. At this point, the decision is typically made in close coordination with legal counsel and, in some agencies, a termination contracting officer.

Excusable delay must be evaluated fairly. The burden of proving the default shifts to the government on appeal. If the contractor raised a plausible excusable delay claim in their show-cause response and the government did not adequately consider it, the termination may be converted to a termination for convenience. Take the response seriously, evaluate each claim on its merits, and document your analysis.

5 The Termination Decision Is Not Yours Alone

The cure notice and show-cause notice are tools the CO uses to build the record. The termination decision itself involves your legal counsel, and in many agencies, a termination contracting officer (TCO) who specializes in termination actions. This is by design. Terminations for default are among the most legally consequential actions in contract administration. The contractor can appeal to a board of contract appeals (ASBCA, CBCA) or the Court of Federal Claims. The government bears the burden of proving the termination was justified.

Your job is to create a record that is clear, specific, and complete. That means:

  • The cure notice identified specific deficiencies with enough detail that anyone reading the record can understand what was wrong
  • The cure period was reasonable for the type of deficiency
  • The show-cause notice accurately described the contractor's failure to cure and gave a fair opportunity to respond
  • The contractor's response was evaluated on its merits and the evaluation was documented
  • Every step was coordinated with legal counsel

If the record is clean, your legal team and TCO have what they need. If the record has gaps (vague deficiency descriptions, unreasonably short cure periods, inadequate evaluation of the contractor's response), the termination is vulnerable on appeal.

What Happens If the Termination Is Overturned If a board or court finds the termination for default was not justified, the standard remedy is to convert it to a termination for convenience. The practical consequence: the contractor gets paid for work performed plus settlement costs, and the government loses its right to recover excess reprocurement costs. A termination for convenience is not a punishment; it is the government saying "we changed our mind." That is why the record matters. A well-documented default termination survives appeal. A poorly documented one becomes an expensive termination for convenience.

6 Cure Notice vs. Show-Cause: Quick Reference

Cure NoticeShow-Cause Notice
PurposeFix this problemTell me why I should not terminate you
FAR authorityFAR 49.402-3(d) and (e)FAR 49.402-3(f)
When usedContractor failing to make progress or perform; delivery date not yet passedAfter cure notice expires without cure, or delivery date has passed
Minimum period10 days (FAR 49.402-3(e))No FAR minimum; typically 10 days
BurdenGovernment states what is wrong; contractor must fix itContractor must justify why termination should not occur
What followsIf not cured: show-cause noticeIf not justified: termination for default decision (with legal/TCO)

Each scenario below presents a situation where a show-cause notice may or may not be the right action. Read the facts, decide the appropriate response, and see the feedback.

Scenario

FAR 49.402-3 — Procedure for Default

The full default procedure including cure notices (subsection d/e), show-cause notices (subsection f), and the termination decision process.

Open FAR 49.402-3 →

FAR 52.249-8(c) — Excusable Delays

Lists the causes that may excuse a contractor's failure to perform: acts of God, acts of the government in its sovereign capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

Open FAR 52.249-8 →

FAR 49.4 — Termination for Default

The full subpart covering the government's right to terminate, procedures, contractor liability, and repurchase against the contractor's account.

Open FAR 49.4 →

FAR 49.402-6 — Repurchase Against Contractor's Account

After termination for default, the government may repurchase from another source and charge the defaulting contractor for excess costs above the original contract price.

Open FAR 49.402-6 →

FAR 49.109 — Settlement of Termination for Default

Covers the settlement process when a termination for default is sustained, including the contractor's liability and the government's rights.

Open FAR 49.109 →

I-20: Cure Notices

The companion training on cure notices. Covers when to issue, required elements, and why the cure notice should be your first step.

Open Cure Notices Training →